Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 5 | 5 | 0.000 | 5 | 0.600 | 0.000 |
22W1361 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : PWD2-BUD/ANBU/34/2023-III-2-PUBLIC WORKS DEPARTMENT-PART (2) 1/123108 E-Fine No. 53170, dt. 19-05-2023
TS Amount (lakhs) : 59.89 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
59.89
Resanction Cost :
59.89
Tentative Cost :
59.89
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 59.79
Demand : 40.00
Allotment : 10.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 70 %
Sanction on :
1 year 1 month ago
19 May 2023
Tentative Completion date:
5 months 1 week from now
30 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 20-Mar-2024
Physical Peramenters