Work Profile Report [22W1361]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : PWD2-BUD/ANBU/34/2023-III-2-PUBLIC WORKS DEPARTMENT-PART (2) 1/123108 E-Fine No. 53170, dt. 19-05-2023
TS Amount (lakhs) : 59.89 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
59.89
Resanction Cost :
59.89
Tentative Cost :
59.89
Exp. Upto Last Fy :
0.10
For CFY 2024-2025
Remaining :
59.79
Demand :
59.00
Allotment :
59.63
Exp in CFY :
59.63
Total Up to Date Exp :
59.73
Work completed
Sanction on : 1 year 7 months ago
19 May 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 5 days 16 minutes from now
30 Dec 2024
Actual Completion Date : 2 months 2 weeks ago
08 Oct 2024
Physical Linear Components
Remark
भौतिक कार्य पूर्ण । -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand