Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 2 | 0 |
22W1369 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 25/54 budget road safety (23-24)
TS Amount (lakhs) : 96.82 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
96.82
Resanction Cost :
96.82
Tentative Cost :
96.82
Exp. Upto Last Fy : 87.60
For CFY 2024-2025
Remaining : 9.22
Demand : 9.22
Allotment : 87.60
Exp in CFY : 0.00
Total Up to Date Exp : 87.60
Construction Started
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 100 %
Sanction on :
1 year 3 weeks ago
20 Jun 2023
Tentative Completion date:
6 months 4 days ago
13 Jan 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण दायित्व शेष -- as on 13-Jul-2024
Physical Peramenters