Work Profile Report [22W1373]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : PWD2-BUD/ANBU/34/2023-III-2-PUBLIC WORKS DEPARTMENT-PART (1) 917/2023 E-File No. 53698, dt. 19-07-2023
TS Amount (lakhs) : 47.43 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
47.43
Resanction Cost :
47.43
Tentative Cost :
47.43
Exp. Upto Last Fy :
16.65
For CFY 2024-2025
Remaining :
30.78
Demand :
30.00
Allotment :
30.52
Exp in CFY :
30.52
Total Up to Date Exp :
47.17
Work completed
Sanction on : 1 year 5 months ago
19 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 3 months 3 weeks ago
31 Aug 2024
Actual Completion Date : 7 months 3 weeks ago
30 Apr 2024
Physical Linear Components
Remark
भौतिक कार्य पूर्ण । -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: