Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3 | 3 | 0.000 | 3 | 0.000 | 0.000 |
22W1376 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : PWD2-BUD/ANBU/34/2023-III-2-PUBLIC WORKS DEPARTMENT-PART (1) 917/2023 E-File No. 53698, dt. 19-07-2023
TS Amount (lakhs) : 38.2 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
38.20
Resanction Cost :
38.20
Tentative Cost :
38.20
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 38.10
Demand : 13.10
Allotment : 13.10
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 15 %
Sanction on :
11 months 4 weeks ago
19 Jul 2023
Tentative Completion date:
1 week 5 days from now
30 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 05-Jul-2024
Physical Peramenters