Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 3.5 | 3.5 | 0.000 | 3.5 | 0.500 | 0.000 |
22W1377 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : PWD2-BUD/ANBU/34/2023-III-2-PUBLIC WORKS DEPARTMENT-PART (1) 917/2023 E-File No. 53698, dt. 19-07-2023
TS Amount (lakhs) : 47.15 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
47.15
Resanction Cost :
47.15
Tentative Cost :
47.15
Exp. Upto Last Fy : 20.31
For CFY 2024-2025
Remaining : 26.84
Demand : 16.00
Allotment : 16.00
Exp in CFY : 0.00
Total Up to Date Exp : 20.31
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 80 %
Sanction on :
11 months 4 weeks ago
19 Jul 2023
Tentative Completion date:
1 week 5 days from now
30 Jul 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 20-Mar-2024
Physical Peramenters