Work Profile Report [22W1377]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : PWD2-BUD/ANBU/34/2023-III-2-PUBLIC WORKS DEPARTMENT-PART (1) 917/2023 E-File No. 53698, dt. 19-07-2023
TS Amount (lakhs) : 47.15 Lacs
Budget Financial Head : Not Available
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
47.15
Resanction Cost :
47.15
Tentative Cost :
47.15
Exp. Upto Last Fy :
47.04
For CFY 2025-2026
Remaining :
0.11
Demand :
0.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
47.04
Construction Started
Sanction on : 1 year 11 months ago
19 Jul 2023
Physical Progress:
At start of FY 2025-2026 :
100 %
Up to Date :
100 %
Tentative Completion date on : 11 months 1 week ago
30 Jul 2024
Actual Completion Date : 9 months 3 weeks ago
10 Sep 2024
Physical Linear Components
Remark
कार्य पूर्ण -- as on 19-Dec-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand