Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.25 | 1.25 | 0.000 | 1.25 | 0.500 | 0.000 |
22W1380 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : PWD2-BUD/ANBU/34/2023-III-2-PUBLIC WORKS DEPARTMENT-5607/2023 E-File No. 53170, dt. 11.08.2023
TS Amount (lakhs) : 17.88 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
17.88
Resanction Cost :
17.88
Tentative Cost :
17.88
Exp. Upto Last Fy : 7.88
For CFY 2024-2025
Remaining : 10.00
Demand : 8.00
Allotment : 8.00
Exp in CFY : 9.88
Total Up to Date Exp : 17.76
Construction Started
Physical Progress:
At start of FY 2024-2025 : 20 %
Up to Date : 100 %
Sanction on :
11 months 6 days ago
11 Aug 2023
Tentative Completion date:
3 weeks 2 days from now
10 Aug 2024
Actual Completion Date:
7 months 1 day ago
16 Dec 2023
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 02-Jul-2024
Physical Peramenters