Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 4.4 | 4.4 | 0.000 | 4.4 | 0.500 | 0.000 |
22W1387 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : PWD2-BUD/ANBU/34/2023-III-2-PUBLIC WORKS DEPARTMENT-5607/2023 E-File No. 53170, dt. 11.08.2023
TS Amount (lakhs) : 49.6 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
49.60
Resanction Cost :
49.60
Tentative Cost :
49.60
Exp. Upto Last Fy : 11.59
For CFY 2024-2025
Remaining : 38.01
Demand : 21.00
Allotment : 21.00
Exp in CFY : 26.02
Total Up to Date Exp : 37.61
Construction Started
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 95 %
Sanction on :
11 months 6 days ago
11 Aug 2023
Tentative Completion date:
3 weeks 2 days from now
10 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर | -- as on 06-Jan-2024