Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.675 | 0.675 | 0.000 | 0.675 | 0.000 | 0.000 |
22W1412 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : PWD2-BUD/ANBU/2/2023-III-2-PUBLIC WORKS DEPARTMENT- E-File No.47985 dt. 07-08-2023
TS Amount (lakhs) : 50.42 Lacs
Financial Detail
Sanction Cost : 50.42 Lacs
Resanction Cost : 50.42 Lacs
Exp. Upto Last Fy : 0.10 Lacs
For CFY 2024-2025
Remaining : 50.32 Lacs
Demand : 30.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 0.10 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
9 months 1 week ago
07 Aug 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति। -- as on 01-Dec-2023
Physical Peramenters