Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.92 | 0.92 | 0.000 | 0.92 | 0.000 | 0.000 |
22W1415 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : PWD2-BUD/ANBU/2/2023-III-2-PUBLIC WORKS DEPARTMENT- E-File No.58555 dt. 08-09-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
44.72
Resanction Cost :
44.72
Tentative Cost :
44.72
Exp. Upto Last Fy : 18.94
For CFY 2024-2025
Remaining : 25.78
Demand : 15.77
Allotment : 6.00
Exp in CFY : 20.02
Total Up to Date Exp : 38.96
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 50 %
Sanction on :
10 months 1 week ago
08 Sep 2023
Tentative Completion date:
9 months 1 week from now
30 Apr 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर -- as on 11-Mar-2024
Physical Peramenters