Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.645 | 0.645 | 0.000 | 0.645 | 0.000 | 0.000 |
22W1419 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : PWD2-BUD/ANBU/2/2023-III-2-PUBLIC WORKS DEPARTMENT- E-File No.58555 dt. 08-09-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
30.29
Resanction Cost :
30.29
Tentative Cost :
30.29
Exp. Upto Last Fy : 3.97
For CFY 2024-2025
Remaining : 26.32
Demand : 13.32
Allotment : 13.32
Exp in CFY : 0.00
Total Up to Date Exp : 3.97
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 30 %
Sanction on :
10 months 1 week ago
08 Sep 2023
Tentative Completion date:
3 months 1 week from now
31 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर -- as on 11-Mar-2024
Physical Peramenters