Work Profile Report [22W1419]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : PWD2-BUD/ANBU/2/2023-III-2-PUBLIC WORKS DEPARTMENT- E-File No.58555 dt. 08-09-2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
30.29
Resanction Cost :
30.29
Tentative Cost :
30.29
Exp. Upto Last Fy :
19.30
For CFY 2025-2026
Remaining :
10.99
Demand :
10.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
19.30
Construction Started
Sanction on : 1 year 7 months ago
08 Sep 2023
Physical Progress:
At start of FY 2025-2026 :
50 %
Up to Date :
100 %
Tentative Completion date on : 5 months 4 weeks ago
31 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर -- as on 11-Mar-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand