Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.7 | 0.7 | 0.000 | 0.7 | 0.000 | 0.000 |
22W1422 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : PWD2-BUD/ANBU/2/2023-III-2-PUBLIC WORKS DEPARTMENT- E-File No.58555 dt. 08-09-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
56.35
Resanction Cost :
56.35
Tentative Cost :
56.35
Exp. Upto Last Fy : 12.05
For CFY 2024-2025
Remaining : 44.30
Demand : 30.00
Allotment : 30.00
Exp in CFY : 19.81
Total Up to Date Exp : 31.86
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 70 %
Sanction on :
10 months 1 week ago
08 Sep 2023
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 20-Mar-2024
Physical Peramenters