Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.56 | 0.56 | 0.000 | 0.56 | 0.000 | 0.000 |
22W1424 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : PWD2-BUD/ANBU/46/2023-III-2-PUBLIC WORKS DEPARTMENT- E-File No.58555 dt. 12-10-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
27.69
Resanction Cost :
27.69
Tentative Cost :
27.69
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 27.59
Demand : 18.00
Allotment : 12.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 50 %
Sanction on :
9 months 5 days ago
12 Oct 2023
Tentative Completion date:
4 months 1 week from now
30 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर -- as on 03-Apr-2024