Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.5 | 0.5 | 0.000 | 0.5 | 0.000 | 0.000 |
22W1425 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : PWD2-BUD/ANBU/46/2023-III-2-PUBLIC WORKS DEPARTMENT- E-File No.58555 dt. 12-10-2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
27.28
Resanction Cost :
27.28
Tentative Cost :
27.28
Exp. Upto Last Fy : 12.17
For CFY 2024-2025
Remaining : 15.11
Demand : 8.00
Allotment : 4.00
Exp in CFY : 0.00
Total Up to Date Exp : 12.17
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 90 %
Sanction on :
9 months 5 days ago
12 Oct 2023
Tentative Completion date:
4 months 1 week from now
30 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 20-Mar-2024