Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.502 | 1.502 | 0.000 | 1.502 | 0.500 | 0.000 |
22W1435 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : PWD2-BUD/ANBU/34/2023-III-2-PUBLIC WORKS DEPARTMENT E-File No.51385 , dt. 27.10.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 54.02 Lacs
Resanction Cost : 54.02 Lacs
Exp. Upto Last Fy : 12.77 Lacs
For CFY 2024-2025
Remaining : 41.25 Lacs
Demand : 20.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 12.77 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
6 months 3 weeks ago
27 Oct 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर -- as on 06-Apr-2024
Physical Peramenters