Work Profile Report [22W1435]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : PWD2-BUD/ANBU/34/2023-III-2-PUBLIC WORKS DEPARTMENT E-File No.51385 , dt. 27.10.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
54.02
Resanction Cost :
54.02
Tentative Cost :
54.02
Exp. Upto Last Fy :
12.77
For CFY 2024-2025
Remaining :
41.25
Demand :
27.00
Allotment :
25.00
Exp in CFY :
6.05
Total Up to Date Exp :
18.82
Construction Started
Sanction on : 1 year 1 month ago
27 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
70 %
Tentative Completion date on : 1 month 4 weeks ago
26 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर -- as on 06-Apr-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: