Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.569 | 0.569 | 0.000 | 0.569 | 0.000 | 0.000 |
22W1436 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : PWD2-BUD/ANBU/34/2023-III-2-PUBLIC WORKS DEPARTMENT- E-File No. 51385 dt. 21.10.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail
Sanction Cost : 29.07 Lacs
Resanction Cost : 29.07 Lacs
Exp. Upto Last Fy : 23.19 Lacs
For CFY 2024-2025
Remaining : 5.88 Lacs
Demand : 5.98 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 23.19 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
6 months 3 weeks ago
27 Oct 2023
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर -- as on 11-Mar-2024
Physical Peramenters