Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
22W1440 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5347/III(2)/2023-01(प्रा०आ०)/2023
TS Amount (lakhs) : 89.88 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
99.12
Resanction Cost :
99.12
Tentative Cost :
99.12
Exp. Upto Last Fy : 31.03
For CFY 2024-2025
Remaining : 68.09
Demand : 68.09
Allotment : 51.00
Exp in CFY : 21.81
Total Up to Date Exp : 52.84
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 45 %
Sanction on :
7 months 1 week ago
05 Dec 2023
Tentative Completion date:
3 months 1 week from now
28 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर -- as on 10-Jun-2024
Physical Peramenters