Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 0 | 0 |
22W1444 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : 5347/III(2)/2023-01(प्रा०आ०)/2023
TS Amount (lakhs) : 59.67 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
75.96
Resanction Cost :
75.96
Tentative Cost :
75.96
Exp. Upto Last Fy : 28.81
For CFY 2024-2025
Remaining : 47.15
Demand : 47.15
Allotment : 37.81
Exp in CFY : 8.62
Total Up to Date Exp : 37.43
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 35 %
Sanction on :
7 months 1 week ago
05 Dec 2023
Tentative Completion date:
3 months 1 week from now
28 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर -- as on 30-Apr-2024
Physical Peramenters