Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.5 | 0.5 | 0.000 | 0.5 | 0.000 | 0.000 |
22W1478 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : E file No 58555/60
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
26.13
Resanction Cost :
26.13
Tentative Cost :
26.13
Exp. Upto Last Fy : 0.10
For CFY 2024-2025
Remaining : 26.03
Demand : 16.00
Allotment : 16.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.10
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 70 %
Sanction on :
4 months 2 weeks ago
01 Mar 2024
Tentative Completion date:
4 months 1 week from now
29 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर है। -- as on 20-Mar-2024
Physical Peramenters