Work Profile Report [22W1572]
Tenders
Project Activities
alerts
Samples
Administrative Approval Detail : E-file No. 70174/60, dt. 23.12.2024
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
74.60
Resanction Cost :
74.60
Tentative Cost :
74.60
Exp. Upto Last Fy :
0.10
For CFY 2025-2026
Remaining :
74.50
Demand :
50.00
Allotment :
50.00
Exp in CFY :
42.75
Total Up to Date Exp :
42.85
Construction Started
Sanction on : 6 months 3 weeks ago
23 Dec 2024
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
65 %
Tentative Completion date on : 3 months 5 days from now
24 Oct 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
जी0एस0बी0 , जी2, जी3 का कार्य पूर्ण, अवशेष कार्य प्रगति पर। -- as on 10-Jul-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand