Work Profile Report [22W1575]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : E file no.81725/56, dt. 27.01.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
50.45
Resanction Cost :
50.45
Tentative Cost :
50.45
Exp. Upto Last Fy :
2.97
For CFY 2025-2026
Remaining :
47.48
Demand :
35.00
Allotment :
0.00
Exp in CFY :
0.00
Total Up to Date Exp :
2.97
Construction Started
Sanction on : 3 months 2 weeks ago
27 Jan 2025
Physical Progress:
At start of FY 2025-2026 :
1 %
Up to Date :
10 %
Tentative Completion date on :
Yet To Decide
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति। -- as on 28-Apr-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: