Work Profile Report [22W1617]
Tenders
Aggrements
Project Activities
alerts
Samples
Administrative Approval Detail : E-file No. 83534/56, dt. 14.05.2025
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
28.99
Resanction Cost :
28.99
Tentative Cost :
28.99
Exp. Upto Last Fy :
0.00
For CFY 2025-2026
Remaining :
28.99
Demand :
28.46
Allotment :
30.93
Exp in CFY :
30.93
Total Up to Date Exp :
30.93
Construction Started
Sanction on : 7 months 1 day ago
14 May 2025
Physical Progress:
At start of FY 2025-2026 :
0 %
Up to Date :
5 %
Tentative Completion date on : 2 months 4 days from now
20 Feb 2026
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 11-Dec-2025
Assets :
Work not linked with IM
Bridges on The Basis of AI: