Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.2 | 1.2 | 0.000 | 1.2 | 0.000 | 0.000 |
22W853 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : श्शासनादेश संख्या 1363/।।। (2)/16-04 (प्रा0आ0)/2015, दिनाॅक 17.03.2016
TS Amount (lakhs) : 851.52 Lacs
Financial Detail
Sanction Cost : 851.52 Lacs
Resanction Cost : 851.52 Lacs
Exp. Upto Last Fy : 792.85 Lacs
For CFY 2024-2025
Remaining : 58.67 Lacs
Demand : 32.00 Lacs
Allotment : 0.00 Lacs
Exp in CFY : 0.00 Lacs
Total Up to Date Exp : 792.85 Lacs
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 0 %
Sanction on :
8 years 2 months ago
17 Mar 2016
Tentative Completion date:
3 years 1 month ago
31 Mar 2021
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति। -- as on 31-Aug-2020
Physical Peramenters