Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Jobs | 1 | 1 | 0 | 1 | 1 | 0 |
23W1022 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-2244(ा)/।।।(2)/20- 66(एम.एल.ए.)/2017 दिनांकः-16.12.2020
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
7.20
Resanction Cost :
7.20
Tentative Cost :
7.20
Exp. Upto Last Fy : 5.35
For CFY 2024-2025
Remaining : 1.85
Demand : 1.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 5.35
Survey work done
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 80 %
Sanction on :
3 years 7 months ago
16 Dec 2020
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पगति पर। -- as on 14-Dec-2022
Physical Peramenters