Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.15 | 2.15 | 2.150 | 0 | 0.000 | 0.000 |
23W1023 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : शा0सं0-2267(ा)/।।।(2)/20- 67(एम.एल.ए.)/2017 टी.सी. ा दिनांकः-06.11.2020
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
145.60
Resanction Cost :
145.60
Tentative Cost :
145.60
Exp. Upto Last Fy : 138.18
For CFY 2024-2025
Remaining : 7.42
Demand : 1.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 138.18
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
3 years 6 months ago
22 Dec 2020
Tentative Completion date:
Yet To Decide
Actual Completion Date:
2 years 1 month ago
01 Jun 2022
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 13-Dec-2022
Physical Peramenters