Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.7 | 0.7 | 0.700 | 0 | 0.000 | 0.000 |
23W1088 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- 2388/ III(2)/20-66 (M.L.A.)/2017
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
15.78
Resanction Cost :
15.78
Tentative Cost :
15.78
Exp. Upto Last Fy : 14.28
For CFY 2024-2025
Remaining : 1.50
Demand : 1.50
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 14.28
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 11 months ago
04 Aug 2021
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 11-Apr-2023
Physical Peramenters