Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 1.000 | 0 | 0.000 | 0.000 |
23W1116 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- 4953/ III(2)/21-66 (M.L.A.)/2017 T.C.
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
54.44
Resanction Cost :
54.44
Tentative Cost :
54.44
Exp. Upto Last Fy : 53.83
For CFY 2024-2025
Remaining : 0.61
Demand : 0.61
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 53.83
Work completed
Physical Progress:
At start of FY 2024-2025 : 100 %
Up to Date : 100 %
Sanction on :
2 years 9 months ago
14 Oct 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 16-Dec-2022