Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 0.000 | 0.000 |
23W1127 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- 6016/ III(2)/21-67 (M.L.A.)/2017 T.C.
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
1060.26
Resanction Cost :
1060.26
Tentative Cost :
1060.26
Exp. Upto Last Fy : 600.00
For CFY 2024-2025
Remaining : 460.26
Demand : 400.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 600.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 25 %
Up to Date : 51 %
Sanction on :
2 years 7 months ago
11 Dec 2021
Tentative Completion date:
Yet To Decide
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
सिंचाई विभाग द्वारा कार्य प्रगति पर। -- as on 12-Sep-2023
Physical Peramenters