Work Profile Report [23W1127]
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- 6016/ III(2)/21-67 (M.L.A.)/2017 T.C.
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
1060.26
Resanction Cost :
1060.26
Tentative Cost :
1060.26
Exp. Upto Last Fy :
600.00
For CFY 2024-2025
Remaining :
460.26
Demand :
385.33
Allotment :
295.46
Exp in CFY :
2.50
Total Up to Date Exp :
602.50
Construction Started
Sanction on : 2 years 11 months ago
11 Dec 2021
Physical Progress:
At start of FY 2024-2025 :
25 %
Up to Date :
65 %
Tentative Completion date on : 4 months 1 week from now
31 Mar 2025
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
नहर कवरिंग का कार्य सिंचाई विभाग द्वारा किया जा रहा है। तत्पश्चात् ही मार्ग निर्माण का कार्य किया जायेगा। -- as on 04-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand