Work Profile Report [23W1134]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- 471/ III(2)/22-66(M.L.A.)/2017 T.C.- IV
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
17.31
Resanction Cost :
17.31
Tentative Cost :
17.31
Exp. Upto Last Fy :
15.91
For CFY 2024-2025
Remaining :
1.40
Demand :
1.40
Allotment :
5.60
Exp in CFY :
5.60
Total Up to Date Exp :
21.52
Work completed
Sanction on : 2 years 11 months ago
07 Jan 2022
Physical Progress:
At start of FY 2024-2025 :
100 %
Up to Date :
100 %
Tentative Completion date on : 1 year 8 months ago
31 Mar 2023
Actual Completion Date : 1 year 8 months ago
26 Mar 2023
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 11-Apr-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand