Work Profile Report [23W1140]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- 471/ III(2)/22-66(M.L.A.)/2017 T.C.- IV
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
46.70
Resanction Cost :
46.70
Tentative Cost :
46.70
Exp. Upto Last Fy :
27.03
For CFY 2024-2025
Remaining :
19.67
Demand :
19.67
Allotment :
21.05
Exp in CFY :
21.05
Total Up to Date Exp :
48.08
Work completed
Sanction on : 2 years 11 months ago
07 Jan 2022
Physical Progress:
At start of FY 2024-2025 :
50 %
Up to Date :
100 %
Tentative Completion date on : 1 year 8 months ago
31 Mar 2023
Actual Completion Date : 8 months 3 weeks ago
30 Mar 2024
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 30-May-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: