Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.7 | 0.7 | 0.700 | 0 | 0.000 | 0.000 |
23W1140 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- 471/ III(2)/22-66(M.L.A.)/2017 T.C.- IV
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
46.70
Resanction Cost :
46.70
Tentative Cost :
46.70
Exp. Upto Last Fy : 27.03
For CFY 2024-2025
Remaining : 19.67
Demand : 19.67
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 27.03
Work completed
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 100 %
Sanction on :
2 years 6 months ago
07 Jan 2022
Tentative Completion date:
1 year 3 months ago
31 Mar 2023
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 30-May-2024
Physical Peramenters