Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.405 | 1.405 | 1.405 | 0 | 0.000 | 0.000 |
23W1148 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/103650/2023 e-file no.- 43713
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
58.32
Resanction Cost :
58.32
Tentative Cost :
58.32
Exp. Upto Last Fy : 47.03
For CFY 2024-2025
Remaining : 11.29
Demand : 11.00
Allotment : 0.00
Exp in CFY : 10.37
Total Up to Date Exp : 57.40
Work completed
Physical Progress:
At start of FY 2024-2025 : 80 %
Up to Date : 100 %
Sanction on :
1 year 4 months ago
02 Mar 2023
Tentative Completion date:
3 months 2 weeks ago
31 Mar 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 02-May-2024
Physical Peramenters