Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.39 | 1.39 | 0.000 | 1.39 | 1.390 | 0.000 |
23W1152 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/103650/2023 e-file no.- 43713
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
62.21
Resanction Cost :
62.21
Tentative Cost :
62.21
Exp. Upto Last Fy : 25.64
For CFY 2024-2025
Remaining : 36.57
Demand : 35.00
Allotment : 0.00
Exp in CFY : 23.43
Total Up to Date Exp : 49.07
Construction Started
Physical Progress:
At start of FY 2024-2025 : 50 %
Up to Date : 100 %
Sanction on :
1 year 4 months ago
02 Mar 2023
Tentative Completion date:
2 months 2 weeks ago
30 Apr 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 27-Jun-2024
Physical Peramenters