Work Profile Report [23W1170]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/119401/2023 e-file no.- 49076
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
14.05
Resanction Cost :
14.05
Tentative Cost :
14.05
Exp. Upto Last Fy :
6.56
For CFY 2024-2025
Remaining :
7.49
Demand :
7.00
Allotment :
5.99
Exp in CFY :
5.99
Total Up to Date Exp :
12.54
Work completed
Sanction on : 1 year 7 months ago
04 May 2023
Physical Progress:
At start of FY 2024-2025 :
40 %
Up to Date :
100 %
Tentative Completion date on : 8 months 2 weeks ago
04 Apr 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य पूर्ण। -- as on 26-Jun-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: