Work Profile Report [23W1172]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/121103/2023 e-file no.- 52003
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
69.80
Resanction Cost :
69.80
Tentative Cost :
58.00
Saving
11.80
Exp. Upto Last Fy :
17.37
For CFY 2024-2025
Remaining :
52.43
Demand :
50.00
Allotment :
13.38
Exp in CFY :
25.29
Total Up to Date Exp :
42.66
Work completed
Sanction on : 1 year 6 months ago
11 May 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 1 month 3 weeks ago
30 Sep 2024
Actual Completion Date : 4 months 3 weeks ago
30 Jun 2024
Physical Linear Components
Remark
Overall Saving 11.8 has been recorded as expected cost of work reduced from 69.8 to 58.00 . -- as on 23-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI: