Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2 | 2 | 0.000 | 2 | 2.000 | 0.000 |
23W1175 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/121103/2023 e-file no.- 52003
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
67.98
Resanction Cost :
67.98
Tentative Cost :
67.98
Exp. Upto Last Fy : 17.08
For CFY 2024-2025
Remaining : 50.90
Demand : 45.00
Allotment : 0.00
Exp in CFY : 24.33
Total Up to Date Exp : 41.41
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
11 May 2023
Tentative Completion date:
2 months 1 week from now
30 Sep 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 14-Jul-2024