Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.328 | 1.328 | 1.320 | 0.008 | 0.000 | 0.000 |
23W1177 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/121103/2023 e-file no.- 52003
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
96.67
Resanction Cost :
96.67
Tentative Cost :
96.67
Exp. Upto Last Fy : 60.59
For CFY 2024-2025
Remaining : 36.08
Demand : 35.00
Allotment : 0.00
Exp in CFY : 2.34
Total Up to Date Exp : 62.93
Work completed
Physical Progress:
At start of FY 2024-2025 : 10 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
11 May 2023
Tentative Completion date:
4 months 2 weeks ago
28 Feb 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 02-May-2024