Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.9 | 1.9 | 1.900 | 0 | 0.000 | 0.000 |
23W1178 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/121103/2023 e-file no.- 52003
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
57.75
Resanction Cost :
57.75
Tentative Cost :
57.75
Exp. Upto Last Fy : 26.26
For CFY 2024-2025
Remaining : 31.49
Demand : 30.00
Allotment : 0.00
Exp in CFY : 23.86
Total Up to Date Exp : 50.12
Work completed
Physical Progress:
At start of FY 2024-2025 : 60 %
Up to Date : 100 %
Sanction on :
1 year 2 months ago
11 May 2023
Tentative Completion date:
2 weeks 3 days ago
30 Jun 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 02-May-2024