Work Profile Report [23W1190]
Remarks
Tenders
Aggrements
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/133749/2023 e-file no.- 53091
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
91.32
Resanction Cost :
91.32
Tentative Cost :
91.32
Exp. Upto Last Fy :
11.73
For CFY 2024-2025
Remaining :
79.59
Demand :
79.00
Allotment :
31.75
Exp in CFY :
42.57
Total Up to Date Exp :
54.30
Construction Started
Sanction on : 1 year 4 months ago
30 Jun 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
40 %
Tentative Completion date on : 4 weeks 2 days ago
24 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 01-Dec-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: