Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.3 | 1.3 | 0.000 | 1.3 | 1.300 | 0.000 |
23W1190 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/133749/2023 e-file no.- 53091
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
91.32
Resanction Cost :
91.32
Tentative Cost :
91.32
Exp. Upto Last Fy : 11.73
For CFY 2024-2025
Remaining : 79.59
Demand : 75.00
Allotment : 0.00
Exp in CFY : 12.70
Total Up to Date Exp : 24.43
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 20 %
Sanction on :
1 year 2 weeks ago
30 Jun 2023
Tentative Completion date:
3 months 6 days from now
24 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 01-Dec-2023
Physical Peramenters