Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.82 | 0.82 | 0.000 | 0.82 | 0.820 | 0.000 |
23W1191 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/133749/2023 e-file no.- 53091
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
55.46
Resanction Cost :
55.46
Tentative Cost :
55.46
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 55.46
Demand : 54.00
Allotment : 0.00
Exp in CFY : 0.00
Total Up to Date Exp : 0.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 20 %
Sanction on :
1 year 2 weeks ago
30 Jun 2023
Tentative Completion date:
8 months 1 week from now
31 Mar 2025
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 01-Dec-2023
Physical Peramenters