Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.985 | 0.985 | 0.000 | 0.985 | 0.980 | 0.000 |
23W1192 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/133749/2023 e-file no.- 53091
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
68.73
Resanction Cost :
68.73
Tentative Cost :
68.73
Exp. Upto Last Fy : 5.93
For CFY 2024-2025
Remaining : 62.80
Demand : 60.00
Allotment : 0.00
Exp in CFY : 2.07
Total Up to Date Exp : 8.00
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 20 %
Sanction on :
1 year 2 weeks ago
30 Jun 2023
Tentative Completion date:
4 months 1 week from now
26 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 01-Dec-2023
Physical Peramenters