Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.5 | 1.5 | 0.000 | 1.5 | 1.500 | 0.000 |
23W1194 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/152057/2023 e-file no.- 43713
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
45.87
Resanction Cost :
45.87
Tentative Cost :
45.87
Exp. Upto Last Fy : 25.17
For CFY 2024-2025
Remaining : 20.70
Demand : 20.00
Allotment : 0.00
Exp in CFY : 18.52
Total Up to Date Exp : 43.69
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
11 months 2 weeks ago
31 Jul 2023
Tentative Completion date:
3 months 1 week from now
30 Oct 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 20-Jun-2024
Physical Peramenters