Work Profile Report [23W1196]
Remarks
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/152057/2023 e-file no.- 43713
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
79.24
Resanction Cost :
79.24
Tentative Cost :
79.24
Exp. Upto Last Fy :
35.54
For CFY 2024-2025
Remaining :
43.70
Demand :
42.00
Allotment :
0.00
Exp in CFY :
24.96
Total Up to Date Exp :
60.50
Construction Started
Sanction on : 1 year 3 months ago
31 Jul 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
80 %
Tentative Completion date on : 4 weeks 2 days ago
24 Oct 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 01-Dec-2023
Assets :
Work not linked with IM
Bridges on The Basis of AI: