Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 0.61 | 0.61 | 0.000 | 0.61 | 0.610 | 0.000 |
23W1203 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/161253/2023, E- File no.- 53091, Date- 12.10.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
53.12
Resanction Cost :
53.12
Tentative Cost :
53.12
Exp. Upto Last Fy : 12.08
For CFY 2024-2025
Remaining : 41.04
Demand : 40.00
Allotment : 0.00
Exp in CFY : 3.75
Total Up to Date Exp : 15.83
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 20 %
Sanction on :
9 months 5 days ago
12 Oct 2023
Tentative Completion date:
4 weeks 1 day from now
16 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 02-May-2024
Physical Peramenters