Work Profile Report [23W1203]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/161253/2023, E- File no.- 53091, Date- 12.10.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
53.12
Resanction Cost :
53.12
Tentative Cost :
39.92
Saving
13.20
Exp. Upto Last Fy :
12.08
For CFY 2024-2025
Remaining :
41.04
Demand :
40.00
Allotment :
29.93
Exp in CFY :
29.93
Total Up to Date Exp :
42.01
Construction Started
Sanction on : 1 year 2 months ago
12 Oct 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
20 %
Tentative Completion date on : 4 months 1 week ago
16 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 24-Oct-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand