Work Profile Report [23W1206]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/167411/2023, E- File no.- 43713, Date- 07.11.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
21.45
Resanction Cost :
21.45
Tentative Cost :
21.00
Saving
0.45
Exp. Upto Last Fy :
11.04
For CFY 2024-2025
Remaining :
10.41
Demand :
10.00
Allotment :
8.20
Exp in CFY :
8.20
Total Up to Date Exp :
19.24
Construction Started
Sanction on : 1 year 2 weeks ago
07 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
80 %
Tentative Completion date on : 3 months 2 weeks ago
08 Aug 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
Overall Saving 0.45 has been recorded as expected cost of work reduced from 21.45 to 21.00 . -- as on 09-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand