Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 1.000 | 0.000 |
23W1206 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/167411/2023, E- File no.- 43713, Date- 07.11.2023
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
21.45
Resanction Cost :
21.45
Tentative Cost :
21.45
Exp. Upto Last Fy : 11.04
For CFY 2024-2025
Remaining : 10.41
Demand : 10.00
Allotment : 0.00
Exp in CFY : 8.20
Total Up to Date Exp : 19.24
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 80 %
Sanction on :
8 months 1 week ago
07 Nov 2023
Tentative Completion date:
3 weeks 19 hours from now
08 Aug 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 02-May-2024
Physical Peramenters