Work Profile Report [23W1208]
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : G.O. no.- I/167411/2023, e- File no.- 43713, Date- 07.11.2023
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : State Sector ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
96.16
Resanction Cost :
96.16
Tentative Cost :
73.00
Saving
23.16
Exp. Upto Last Fy :
61.45
For CFY 2024-2025
Remaining :
34.71
Demand :
32.00
Allotment :
23.97
Exp in CFY :
18.58
Total Up to Date Exp :
80.03
Work completed
Sanction on : 1 year 2 weeks ago
07 Nov 2023
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
100 %
Tentative Completion date on : 7 months 1 week ago
15 Apr 2024
Actual Completion Date : 5 months 3 weeks ago
30 May 2024
Physical Linear Components
Remark
Overall Saving 23.16 has been recorded as expected cost of work reduced from 96.16 to 73.00 . -- as on 09-Aug-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand