Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 2.2 | 2.2 | 0.000 | 2.2 | 2.200 | 0.000 |
23W1212 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/176048/2023 e-file no.- 62543
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
47.53
Resanction Cost :
47.53
Tentative Cost :
47.53
Exp. Upto Last Fy : 0.00
For CFY 2024-2025
Remaining : 47.53
Demand : 45.00
Allotment : 0.00
Exp in CFY : 9.40
Total Up to Date Exp : 9.40
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 80 %
Sanction on :
6 months 4 weeks ago
18 Dec 2023
Tentative Completion date:
3 months 3 weeks from now
12 Nov 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 02-May-2024
Physical Peramenters