Work Profile Report [23W1216]
Remarks
Tenders
Project Activities
alerts
Documents
Samples
Administrative Approval Detail : Letter no.- 2104/J.Y./Anu.Sansodhan/2023-24
TS Amount (lakhs) : 0 Lacs
Budget Financial Head : SRMD ⮚
Financial Detail
(All Amount in Rs Lakhs)
Sanction Cost :
40.00
Resanction Cost :
40.00
Tentative Cost :
40.00
Exp. Upto Last Fy :
0.00
For CFY 2024-2025
Remaining :
40.00
Demand :
16.00
Allotment :
20.00
Exp in CFY :
20.00
Total Up to Date Exp :
20.00
Construction Started
Sanction on : 9 months 1 week ago
12 Mar 2024
Physical Progress:
At start of FY 2024-2025 :
0 %
Up to Date :
60 %
Tentative Completion date on : 3 weeks 3 days ago
30 Nov 2024
Actual Completion Date :
Not Yet Reported
Physical Linear Components
Remark
कार्य प्रगति पर। -- as on 02-May-2024
Assets :
Work not linked with IM
Bridges on The Basis of AI:
© PWD Uttarakhand