Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.85 | 1.85 | 0.000 | 1.85 | 1.850 | 0.000 |
23W1218 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/191519/2024 e-file no.- 68310
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
96.94
Resanction Cost :
96.94
Tentative Cost :
96.94
Exp. Upto Last Fy : 18.05
For CFY 2024-2025
Remaining : 78.89
Demand : 75.00
Allotment : 0.00
Exp in CFY : 16.60
Total Up to Date Exp : 34.65
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 40 %
Sanction on :
4 months 3 weeks ago
20 Feb 2024
Tentative Completion date:
4 months 3 weeks from now
10 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 02-May-2024
Physical Peramenters