Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 1.000 | 0.000 |
23W1219 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/191519/2024 e-file no.- 68310
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
24.14
Resanction Cost :
24.14
Tentative Cost :
24.14
Exp. Upto Last Fy : 10.73
For CFY 2024-2025
Remaining : 13.41
Demand : 13.00
Allotment : 0.00
Exp in CFY : 9.43
Total Up to Date Exp : 20.17
Work completed
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 100 %
Sanction on :
4 months 3 weeks ago
20 Feb 2024
Tentative Completion date:
4 months 3 weeks from now
10 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य पूर्ण। -- as on 20-Jun-2024
Physical Peramenters