Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1 | 1 | 0.000 | 1 | 1.000 | 0.000 |
23W1220 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/191519/2024 e-file no.- 68310
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
23.63
Resanction Cost :
23.63
Tentative Cost :
23.63
Exp. Upto Last Fy : 9.13
For CFY 2024-2025
Remaining : 14.50
Demand : 13.00
Allotment : 0.00
Exp in CFY : 11.77
Total Up to Date Exp : 20.89
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 20 %
Sanction on :
4 months 3 weeks ago
20 Feb 2024
Tentative Completion date:
4 months 2 weeks from now
03 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 02-May-2024
Physical Peramenters