Particulars | Sanction | Resanction | Upto Last Fy | For Cfy 2024-2025 | ||
---|---|---|---|---|---|---|
Remaining | Target | Achievement | ||||
Length of Road [Km] | 1.55 | 1.55 | 0.000 | 1.55 | 1.550 | 0.000 |
23W1222 :
Work not linked with IM
Bridges on The Basis of AI:
Administrative Approval Detail : G.O. no.- I/191519/2024 e-file no.- 68310
TS Amount (lakhs) : 0 Lacs
Financial Detail (in Rs Lakhs)
Sanction Cost :
32.56
Resanction Cost :
32.56
Tentative Cost :
32.56
Exp. Upto Last Fy : 10.95
For CFY 2024-2025
Remaining : 21.61
Demand : 20.00
Allotment : 0.00
Exp in CFY : 9.30
Total Up to Date Exp : 20.24
Construction Started
Physical Progress:
At start of FY 2024-2025 : 0 %
Up to Date : 40 %
Sanction on :
4 months 3 weeks ago
20 Feb 2024
Tentative Completion date:
4 months 3 weeks from now
10 Dec 2024
Actual Completion Date:
Not Yet Reported
Remark
Bottelneck: no issue
कार्य प्रगति पर। -- as on 02-May-2024
Physical Peramenters